Pardon our dust! There are a number of major (and minor) construction projects taking place in and around Saginaw. To keep you informed, we are connecting you to information about projects (listed below) that either might interest you or that might effect your day.

Recent Archives

Capital Projects in Saginaw

Updated June 9, 2020

Knowles Drive (Phase 1-3)

Schedule & Notes

Old Decatur North Expansion

Schedule & Notes

  • Estimated Project Advertisement:  December 2020
  • Working on drainage area maps and preliminary drainage evaluation.
  • Submitted updated concept plan showing updated roadway cross section and layout based on current adjacent planned development.
  • Working on preparing preliminary plans.

Old Decatur and WJ Boaz Intersection Improvements

Schedule & Notes

  • Design NTP May 20, 2020
  • Design survey is underway.

ADA Phase 3A Evaluation

Schedule & Notes

East Cement Creek Improvements

Schedule & Notes

  • Estimated Project Advertisement:  July 2020
  • City is obtaining easements to allow Oncor to relocate facilities. KHA is coordinating with other franchises to get relocated. KHA is preparing 90% plans for both Phases for City.

Saginaw Blvd. 16-inch Water Line Phase 2

Schedule & Notes

  • Estimated Project Advertisement:  July 2020
  • Plans and construction documents are 95% complete.  Waiting on final approval from Union Pacific to obtain permit. After Union Pacific permit is obtained, easement documents can be executed with Ardent Mills. Project can be advertised after easements are executed.

Bailey Boswell Overpass

Schedule & Notes

McLeroy Curb Replacement

Schedule & Notes

  • Project Award:  May 19, 2020
  • Pre-construction meeting was held on May 26, 2020. Notice to proceed anticipated for June 8, 2020.

Police Department Parking Lot

Schedule & Notes

  • Project Complete

Fairmount 15-inch Sewer Phase 1

Schedule & Notes

  • Project Complete

FM 156 Coordination and Utility Relocation

Schedule & Notes

  • Estimated Walk Through:  June 9, 2020
  • Majority of work complete. Scheduling final walk through.